98  Practical Power System and Protective Relays Commissioning


























            FIGURE 7.14 Time measurement connection to measure the operating times of circuit breakers.

            time—this device measures and records the time and timing diagram. The
            test is done at 100% of voltage substation DC voltage and 80% of voltage
            substation DC voltage, as well as at 60% of voltage substation DC voltage
            and at 80% there should be no any pole discrepancy in three-phase closing
            and three-phase tripping.
               The  obtained  close/open  time  should  be  compared  with  the
            manufacturer’s reference values or factory test results. Refer to Fig. 7.14 for
            CB timing tester connection to measure the operating times of CB.



            7.6.5 Reduced Voltage Test

            This test is carried out to confirm the operation of the closing coil of the cir-
            cuit breaker when reducing the control dc voltage of the circuit breaker. A
            reduced voltage of 80% of the rated voltage for the closing coil and 60% of
            the rated voltage for the trip coil at these two values of the voltage the
            breaker should be able to operate (close and open).