Circuit Breakers Theory Testing and Commissioning Chapter | 7  97

















































             FIGURE 7.13 Test connections for circuit breaker in a closed condition.
             occur under abnormal voltage conditions during system operations. The high-
             potential test should be the final test performed after all repairs have been
             made and a successful insulation resistance test has been carried out. The
             maintenance test voltage should be 75% of the factory test voltage and the
             time duration should be 1 minute. For example, for 13.8 kV the factory test
             voltage will be at 36 kV and the maintenance test voltage will be at 27 kV.

             7.6.4 Circuit Breaker Timing Test

             This test is performed to verify the open and closing times of CB contacts. It
             is done using a CB timing tester to measure the closing time and tripping