Page 120 - Practical Well Planning and Drilling Manual
P. 120

Section 1 revised 11/00/bc  1/17/01  2:56 PM  Page 96








                      [      ]
                       1.4.22     Well Design



                       1.4.22.  Wellheads: General Descriptions

                           Spool type surface wellhead. On a land or platform rig where the
                       wells are drilled from the platform, surface wellheads will generally be
                       used. The conductor pipe extends to surface (land rig cellar or plat-
                       form wellhead deck). Surface casing is cemented inside this, and a weld
                       or screw-on spool is attached after cutting the conductor to a conve-
                       nient height.
                           On a land rig, surface casing will generally be cemented to surface.
                       On a platform, small tubing is usually run in the casing-conductor
                       annulus and cement flushed out to seabed.
                           Subsequent casing strings are landed in the previous spool, and so
                       the surface casing spool will ultimately bear loads from all the casings
                       and the completion and Xmas tree.
                           Compact surface wellhead. The compact wellhead offers several
                       advantages over the spool type wellhead, including:

                           1. Reduced time nippling up/down
                           2. Safer—no need to flange up an extra spool after each casing job

                           The compact wellhead functions much like a subsea wellhead or
                       mudline suspension.
                           Mudline suspension system. A mudline suspension system may
                       be used when a well is drilled offshore for later completion after
                       installing a platform. It can be run into a template set on the seabed
                       that allows several wells to be drilled before the platform is installed. If
                       drilling and platform construction can take place together, the time to
                       get the field on stream is reduced.
                           The conductor is cemented in a drilled hole or driven to depth.
                       Below the mudline within the conductor is a landing ring that has an
                       internal profile allowing hangers to be set. As subsequent casings are
                       run they locate on top of the previous hanger. The hangers are run on
                       a running tool attached to a string of casing back to the rig.
                           To move the rig off location the casing strings above the hangers
                       are backed out and recovered, with a suspension cap put in place after
                       the last casing has been pulled. The conductor is cut above the landing
                       ring. This leaves the well suspended at the mudline. When the platform
                       is installed, the casing strings are rerun after recovering the suspension
                       cap and the well can be completed.