                      [      ]  Well Programming
                       2.1.1



                       General information:

                          Country, concession, rig, program issue date, and who it is written by
                          Drilling reporting requirements
                          General points on safety and inspection requirements
                          Offset wells used for input
                          Statement on shallow gas (e.g., whether considered likely to be pre-
                          sent or not)


                       Well identification:

                          Field, block, permit, location coordinates, platform, conductor/slot
                          number, well number, and well type (exploration, appraisal, devel-
                          opment, infill, injector, etc.)

                       Well objectives:


                          Priority order of objectives (short text); include well objectives as
                          well as production or exploration
                          Planned drilling time breakdown (time/depth curve)
                          Estimated cost breakdown (cost/depth curve and costs by category)

                       Potential hazards or problems during drilling operations (not specific to
                       one hole section):

                          Note any hazards that remain; how to monitor; recovery procedures
                          if the potential hazard occurs (could be suspected presence of H S
                                                                                      2
                          or drilling HPHT for instance)
                          Concurrent operations (e.g., drilling on a platform while production
                          or construction work is ongoing) would also be a potential hazard
                          and must be identified with references to safe working procedures


                       Well positioning:

                          Surface coordinates (with reference system) and tolerances
                          Datum level (lowest astronomical tide, mean sea level, etc.)
                          Rig floor elevation relative to datum level
                          Water depth