Section 3 revised 11/00/bc  1/17/01  12:00 PM  Page 381














                                                                       [ ]


                                                                           3.4





















                                                                             Casing




                       3.4.1.  Conductor Placement


                           There are three current techniques of setting conductor pipe: jet-
                       ting in, piledriving or drilling, and cementing to surface. Criteria for
                       drilling, jetting, or driving relate to the desired setting depth and
                       whether the topsoil conditions allow jetting or driving to this depth
                       without damaging the conductor drive shoe. (Refer to the information
                       on individual casing points in Section 1.4.6.)
                           Offshore conductor; preparation for the job. The job can be done
                       faster and cheaper if the proper preparations are made. Preparations in
                       advance of the rig arrival include the following:

                       1. Make a decision on what connections will be used and where the
                          conductor will be welded while driving. If welded, then the pipe
                          ends should be prepared by beveling for welding before sending to
                          the rig. Otherwise, a beveling machine needs to be sent out. If
                          connections are to be used then all the information and equip-
                          ment needed to run the connection has to be organized.


                                                      381
   400   401   402   403   404   405   406   407   408   409   410