Appendix NEW! revised 11/00/bc  1/30/01  3:29 PM  Page 447














                                                    [    ]


                                                       Appendix:4





















                                          Drilling Equipment Lists

                                                                by Operation

                           The equipment lists shown in Table A-2 is meant as a guide to
                       assist the on-site drilling supervisor and onshore base manager. It
                       should not be assumed that the list is complete, and it is the responsi-
                       bility of the drilling supervisor to ensure that all required equipment
                       has been obtained.
                           Note that the table shows the estimated quantity for each opera-
                       tion; in some cases these items will already be on the rig for a previous
                       operation so only the deficient amount need be sent.

                       Table A-2  Drilling Equipment


                                    Rig Positioning and Preparation for Operations
                        Item  Qty   Description                          Comments
                        1     A/R   Positioning equipment as required for
                                    rig and anchor running vessels
                        2     1     Rig communications package
                        3     1     ROV, if required