Page 59 - Root Cause Failure Analysis
P. 59

50       Root Cause Failure Analysis
                   Labor  Incremental labor costs should include all unusual costs incurred to operate,
                   maintain, or  repair the  machine or  system being  investigated. These costs should
                   include overtime premium, contract labor, outside vendor or shop support, and any
                   other costs above the normal operating and maintenance budget that were incurred as
                   a result of the abnormal behavior of the machine or system.

                   Capacity Loss  Many  equipment  and  other  process-related  problems  result  in
                   decreased product output, or capacity. In the cost analysis, capacity losses should
                   be defined both in terms of production units (Le., tons, pounds, etc.) and actual rev-
                   enue losses (i.e., dollars). Using both of these measures provides a true picture of
                   the situation.

                   An accurate estimate of the total downtime, including testing following the repair and
                   reduced-capacity startups, is essential for this phase of the evaluation. However, the
                   normal tendency is to estimate the actual time required to repair, replace, or modify
                   the system but to omit the inherent problems that will be encountered during the startup
                   process.

                   Startups following any  major activity, such as  a  repair, upgrade, or  modification,
                   rarely are trouble free. Production capacity almost always is lost while “glitches” are
                   corrected. In  some  cases,  the  losses  caused  by  startup problems are  signijicantly
                   greater than those incurred simplyfrom the maintenance activity. There are two via-
                   ble ways to determine this cost.

                   The first is to use the plant’s business plan to obtain the planned production rate for
                   the area or system under investigation. Most business plans define a rated or planned
                   capacity, usually expressed in terms of production units per time (i.e., poundshour).
                   The logic used to develop these capacity rates vary from plant to plant, but typically
                   they are a weighted rate based on demand, seasonal variations in business, and histor-
                   ical data. In some cases, the rate will be substantially below the actual design capacity
                   of the system.

                   The second method is to use the design-capacity rates defined in the design review.
                   This approach is more accurate since it is based on actual design limitations. The
                   functional specifications of each production system within the plant define minimum,
                   mean, and maximum capacity rates. In most cases, the mean or average capacity rate
                   is used when developing the cost analysis. This approach is conservative and easily
                   can be justified.

                   Delivery-Schedule Slippage  Although capacity loss is a critical element because of
                   its impact on cash flow and profitability, another important consideration is the deliv-
                   ery schedule. Customers expect on-time deliveries and may cancel orders if schedules
                   are  not  met,  adding  further  impact to  the  cash  flow  and  profitability. Therefore,
                   extreme caution should be exercised if the downtime required to implement a poten-
                   tial corrective action has a significant effect on delivery schedules.
   54   55   56   57   58   59   60   61   62   63   64