Notes  Scoping will  require more  effort/time





                          Effort  allocated  2 p-d  1 p-d  1 p-d  1.5 p-d  2 p-d  1 p-d  1.5 p-d  2 p-d  3 p-d  3 p-d  3 p-d



                          Assigned  person  BLS  JPP  BLS/JPP  BLS  JPP  MLL  BLS  JPP  MLL  all  all





                          Actual  complete  wk1, d2  wk1, d2  wk1, d3  wk1, d3



                          Planned  complete  wk1, d2  wk1, d2  wk1, d3  wk1, d3  wk2, d2  wk2, d2  wk2, d3  wk2, d2  wk2, d3  wk2, d3  wk2, d3  wk2, d4  wk2, d5




                          Actual  start  wk1, d1  wk1, d2  wk1, d3  wk1, d3  wk1, d4  wk1, d3  wk1, d4



                          Planned  start  wk1, d1  wk1, d2  wk1, d3  wk1, d3  wk1, d4  wk1, d3  wk2, d1  wk2, d1  wk1, d4  wk2, d1  wk2, d3  wk2, d4  wk2, d5












                            Work tasks     Define desired output/control/input (OCI)  An example project table

                                 Identify needs and benefits  Meet with customers Identify needs and project constraints Establish product statement Milestone: Product statement defined  Scope keyboard functions Scope voice input functions Scope modes of interaction Scope document diagnostics Scope other WP functions  Document OCI FTR: Review OCI with customer Revise OCI as required Milestone: OCI defined Define the func










                                 I.1.1     I.1.2               I.1.3           FIGURE 7.5