Page 217 -
P. 217
188 PART TWO MANAGING SOFTWARE PROJECTS
tasks. Any errors that are not uncovered (but found in later tasks) are considered to
be defects, D. Defect removal efficiency (Chapter 4) has been defined as
DRE = E/(E + D)
DRE is a process metric that provides a strong indication of the effectiveness of
quality assurance activities, but DRE and the error and defect counts associated with
it can also be used to assist a project manager in determining the progress that is
being made as a software project moves through its scheduled work tasks.
Let us assume that a software organization has collected error and defect data
over the past 24 months and has developed averages for the following metrics:
• Errors per requirements specification page, E req
• Errors per component—design level, E design
• Errors per component—code level, E code
• DRE—requirements analysis
• DRE—architectural design
• DRE—component level design
• DRE—coding
As the project progresses through each software engineering step, the software team
records and reports the number of errors found during requirements, design, and
code reviews. The project manager calculates current values for E req , E design , and
E code . These are then compared to averages for past projects. If current results vary
by more than 20% from the average, there may be cause for concern and there is cer-
tainly cause for investigation.
For example, if E req = 2.1 for project X, yet the organizational average is 3.6, one
of two scenarios is possible: (1) the software team has done an outstanding job of
developing the requirements specification or (2) the team has been lax in its review
approach. If the second scenario appears likely, the project manager should take
The more quantitative immediate steps to build additional design time 12 into the schedule to accommodate
your approach to the requirements defects that have likely been propagated into the design activity.
project tracking and
control, the more likely These error tracking metrics can also be used to better target review and/or test-
you’ll be able to ing resources. For example, if a system is composed of 120 components, but 32 of
foresee potential these component exhibit E design values that have substantial variance from the aver-
problems and respond age, the project manager might elect to dedicate code review resources to the 32
to them proactively. components and allow others to pass into testing with no code review. Although all
Use earned value and
tracking metrics. components should undergo code review in an ideal setting, a selective approach
(reviewing only those modules that have suspect quality based on the E design value)
might be an effective means for recouping lost time and/or saving costs for a proj-
ect that has gone over budget.
12 In reality, the extra time will be spent reworking requirements defects, but the work will occur
when the design is underway.