Page 220 -
P. 220

CHAPTER 7  PROJECT SCHEDULING AND TRACKING                         191

                                a. Define parallel work activities during the OLCRS project.
                                b. Distribute effort throughout the project.
                                c. Establish milestones for the project.

                              7.8. Using Section 7.3 as a guide compute the TSS for OLCRS. Be sure to show all
                              of your work. Select a project type and an appropriate task set for the project.

                              7.9. Define a task network for OLCRS, or alternatively, for another software project
                              that interests you. Be sure to show tasks and milestones and to attach effort and dura-
                              tion estimates to each task. If possible, use an automated scheduling tool to perform
                              this work.
                              7.10. If an automated scheduling tool is available, determine the critical path for the
                              network defined in problem 7.7.
                              7.11. Using a scheduling tool (if available) or paper and pencil (if necessary), develop
                              a timeline chart for the OLCRS project.
                              7.12. Refine the task called “technology risk assessment” in Section 7.4 in much the
                              same way as concept scoping was refined in Section 7.5.

                              7.13. Assume you are a software project manager and that you’ve been asked to
                              compute earned value statistics for a small software project. The project has 56
                              planned work tasks that are estimated to require 582 person-days to complete. At
                              the time that you’ve been asked to do the earned value analysis, 12 tasks have been
                              completed. However the project schedule indicates that 15 tasks should have been
                              completed. The following scheduling data (in person-days) are available:
                              Task   Planned effort   Actual effort
                                1     12.0          12.5
                                2     15.0          11.0
                                3     13.0          17.0
                                4      8.0           9.5
                                5      9.5           9.0
                                6     18.0          19.0
                                7     10.0          10.0
                                8      4.0           4.5
                                9     12.0          10.0
                               10      6.0           6.5
                               11      5.0           4.0
                               12     14.0          14.5
                               13     16.0            —
                               14      6.0            —
                               15      8.0            —
                              Compute the SPI, schedule variance, percent scheduled for completion, percent com-
                              plete, CPI, and cost variance for the project.
                              7.14. Is it possible to use DRE as a metric for error tracking throughout a software
                              project? Discuss the pros and cons of using DRE for this purpose.
   215   216   217   218   219   220   221   222   223   224   225