Page 143 - Solar Power in Building Design The Engineer's Complete Design Resource
P. 143

SOLAR POWER DESIGN   113



               ■ PV module area: 14 ft 2
               ■ Approximate available unshaded platform space: 7500 ft 2
               ■ Total number of PV modules to be installed: 530 units
               ■ Total PTC output watts: 530 × 158.3 = 83,899 W
               ■ Inverter unit capacity chosen: 100 kilowatts (kW)
               ■ Inverter efficiency: 94.5%
               ■ Total eligible rebate watts: 83,899 × 94.5% = 79,285 W
               ■ Adjusted incentive rebate per watt: $2.50
               ■ Total rebate eligibility: 79,285 × $2.50 = $198,212.50

                  Note that the maximum allowable rentable solar energy is regulated and capped by
               various rebate administrative agencies. For instance, Nevada Power caps the small
               commercial rebate to 30 kW per user meter, whereas the Los Angeles Department of
               Water and Power caps it to a maximum of 300 kW per user per meter and Southern
               California Gas and Southern California Edison limit the cap to 1000 kW per user
               address or meter per year.
                  It is suggested that the solar power design engineers before commencing their
               design should familiarize themselves with the specific requirements of energy service
               providers.
                  Additional documents that must be provided with the rebate application form are as
               follows:


               ■ Electric power system single-line diagrams that show solar power PV arrays, dc
                  combiner boxes, inverters, ac combiner boxes, conduit sizes, feeder cable sizes
                  and associated voltage drops, the solar power fused service disconnect switch,
                  the solar power meter, and the main service switchgear solar disconnect circuit
                  breaker.
               ■ Total building or project electrical demand load calculations (TBDL)
               ■ Calculated percentage ratio of the total eligible rebate watts: (TERW/TBDL) × 100.
                  This figure is required to confirm that the overall capacity of the solar power cogen-
                  eration does not exceed 125 percent of the total project or building electrical
                  demand load.
                  In order to protect the client and avoid design error and omission liabilities, it is
               suggested that all documents and calculations be prepared by an experienced, quali-
               fied, registered electrical engineer.
               Example of a solar power design Upon the approval and confirmation of the
               rebate by the energy service provider, the solar power engineer must undertake a com-
               prehensive study of the entire solar power system and provide the following design
               documentation and paperwork to the agency for final incentive rebate approval. Note
               that times for submitting the required documents outlined here are mandatory, and
               they must be completed within a specified period of limited time.
                  To start the final solar power design, the electrical or solar power designer must
               conduct a thorough solar shading evaluation. If the solar platform is surrounded by
   138   139   140   141   142   143   144   145   146   147   148