Page 212 - Sustainable On-Site CHP Systems Design, Construction, and Operations
P. 212

Electrical Design Characteristics and Issues     185


             upon a step load increase, and conversely with an increase in voltage and frequency
             upon a step load decrease. If the step load is large (approximately 20 to 25 percent of the
             generator set rating) the transients seen by the generator will be measurable and may
             cause a trip of the generator breaker. On the other hand, if the step load is small (less
             than 5 percent of the generator rating) the transients will be barely noticeable. When the
             CHP generator is operating in parallel with the utility, the step load transients as seen
             by the generator will be small, because the utility is, again, practically an infinite bus.
             However, if the system is designed such that the CHP generator may see large step
             loads (the addition of an electric power–driven chiller, for example) when not in parallel
             with the utility, the system must be designed to be able to handle the large transients
             that will occur. Alternatively, the distribution system must be designed to limit the size
             of step loads, via variable frequency drives or soft starters.

             Black start Generator
             Switchgear also needs to allow for connection of another special power generation
             source in large CHP plants (greater than 1 MW), particularly those using a combustion
             turbine generator. In a CHP facility of this size, a potential (and not uncommon) situa-
             tion is that the facility is receiving all of its energy from the CHP source because the
             utility source is unavailable (perhaps, due to a utility system-wide outage). If a subse-
             quent fault in the CHP system temporarily shuts down the plant, the plant operators
             will desire to restart the CHP generator(s) as quickly as possible since at that particular
             time it is the sole source of power to the facility. However, because the utility source is
             unavailable, there is no power for the pumps and starter motors required to restart a
             combustion turbine generator. Therefore, a separate black start generator is a critical
             design consideration and a must to the electrical system. This generator condition is
             called “black start” because its only use is to provide starter power for a separate
             generation system in event of a blackout. The black start generator and an automatic
             transfer switch connected directly to the CHP plant motor control center is another
             aspect of the switchgear design needing consideration.

             Controls
             To optimize a CHP system in a mode in which both utility and CHP sources feed into
             the switchgear, the control system has a major role in controlling the interaction between
             utility (purchased) power and internally self-generated power. For example, in a peak
             shaving system the demand for utility power must be monitored to ensure that the limit
             for a given period does not exceed whatever the contract value set between the utility
             and the facility. Accomplishing this may entail a load-shedding scheme, where the
             switchgear controls automatically open predetermined circuit breakers (i.e., loads) if
             the CHP system does not have enough capacity to carry demand peaks above and
             beyond the utility contracted amount.
                There are a number of possible components in a CHP switchgear application related
             to controls, power quality optimization, and energy management. Tie circuit breakers
             and demand controls were mentioned earlier. Another key component is remote breaker
             control, which allows an operator in the CHP control room to open or close either input
             or distribution output circuit breakers. This allows quick response by a system operator,
             when sometimes monitoring the system 24 hours a day, to a potential problem without
             requiring maintenance staff to be dispatched to the electrical room. Yet another option
             is demand load metering on all of the distribution circuit breakers. Having precise
   207   208   209   210   211   212   213   214   215   216   217