Page 259 - Sustainable On-Site CHP Systems Design, Construction, and Operations
P. 259

232    C o ns truction


             construction and complete the CHP project in a timely manner. Sophisticated methods
             of scheduling, such as the critical path method (CPM), are widely used to plan activities
             and forecast critical delays. When properly used, the project schedule is a management
             tool that enables the owner to obtain advance warning of situations that may threaten
             the profitability of the project.
                A question that is frequently asked in the scheduling area is whether or not the
             owner-operator should approve the schedule of the contractor. There are compelling
             reasons as to why an owner-operator should not approve the schedule. Several courts
             have held that if the parties agree that the CPM schedule is a reasonable plan for per-
             forming the work, the schedule is presumed correct. Because the owner-operator has no
             control over construction means, methods, man-hour loading or economic restraints, it
             is virtually impossible for an owner to be in a position to vouch as to the validity of the
             schedule. Nor would an owner want to be responsible for the contractor’s schedule,
             since the owner’s true concern should be the date that completion milestones will actu-
             ally be met not how the contractor intends to achieve such milestones.
                It is, however, critical for the owner-operator to evaluate the schedule and deter-
             mine whether the owner is being required to perform services in a manner consistent
             with the terms of the contract. For example, the schedule could call for a turnaround
             time on approvals of submittals in a shorter time than is reasonable, placing the owner-
             operator in a position of delaying the contractor. Moreover, care should be taken to
             determine if the dates for bringing fuel to the site (which typically the owner-operator
             or developer’s responsibility) is consistent with the other agreements the owner has
             entered into for the CHP project.
                The project schedule should also be used as analytical device claim recognition,
             preparation, and as proof. This will enable the owner-operator to have objective data as
             to whether delays are excusable under the contract, and will allow the owner to deter-
             mine in advance if the project will be delayed by proposed changes.
                Special care must be taken by the owner-operator who has assumed the risk of con-
             tracting with various parties, such as equipment vendors and an erection contractor, to
             complete the construction of the project. In these multi-prime contracting projects, the
             owner is generally considered to assume duties analogous to those of the normal prime
             (general) contractor with regards to schedule and coordination of the work. The owner-
             operator’s responsibility in this regard includes taking steps to require timely completion
             of one prime’s work to prevent delay or interference to another prime contractor, as well
             as scheduling work in a way that will allow each subcontractor to perform economically
             where their respective work physically interrelates with that of other subcontractors.

             Documentation
             Another important administration tool for avoiding risks on the construction project is
             the creation, transmittal, control, and retention of project records and documents. During
             construction, a construction owner should establish and maintain systems that (a) iden-
             tify the type, quality, frequency, and distribution of the records to be handled, (b) ensures
             that disciplined standards of documentation and proof are maintained, and (c) ensures
             that records are being preserved daily on every element of project administration and
             performance to permit a third party to reconstruct the project from the files, if necessary.
                The records maintained on the project should include general correspondence, sched-
             ules and updates, minutes of job or coordination meetings, daily and weekly reports,
             memoranda for record, job diaries, progress photographs or videos, test and inspection
   254   255   256   257   258   259   260   261   262   263   264