Page 279 - Sustainable On-Site CHP Systems Design, Construction, and Operations
P. 279

252    C o ns truction



                                                       Assumptions
                                                         about the
                   Sample of       Modifications to take  proposed project
                  past projects    account of time and
                                        quality
                     Current
                    information                     Proposed project
                   obtained from                    (quantitative and      COST
                  specialists and                     qualitative)         PLAN
                    suppliers
                                  Forecast of future
                                    inflation and
                                  industrial workload

             FIGURE 15-1  Cost planning process schematic.


                    the mean and as a result one has to have a reasonable idea about the variability
                    of the data.
                       The normal distribution is most useful when one has a high level of confidence
                    about the most likely price. The normal distribution uses the standard deviation,
                    which has 68 percent of all values within 1 standard deviation either side of the
                    mean. Accordingly, one’s experience can be used that there is a 68 percent
                    chance that the price will be within 1 standard deviation of the mean. A peaked
                    distribution will have a smaller standard deviation and large standard deviation
                    will have a lower, flatter top, and cover a broader area at its base. The bell-curve
                    can also be asymmetrical (either to the right or left of the mean). This situation
                    relates to the skewness of the distribution. Standard statistical measures can be
                    used to cope with the skewness and a thorough discussion of its features can be
                    found in the references discussed earlier.
                A cost planning schematic is shown in Fig. 15-1.


        Use of Risk Analysis to Establish Most Likely Cost
             The cost A of construction work is a combination of what the client is either able or
             prepared to pay and the cost B at which the CHP plant contractor is prepared to under-
             take the work in order to show an acceptable level of profit. Accordingly, both costs (A
             and B) can be considered as residing in a community of costs, where there will be both
             extremes, for example, minimum or maximum and a most likely cost.
                Prospective CHP plant owners generally assume that the budgetary construction
             cost estimates established at the completion of the CHP plant design stage represent the
             most likely cost. Yet they along with the proposing CHP plant contractor are also aware
             of the possibility that the actual resulting construction cost will either be exceeded or
             found below design completion stage cost forecast.
                If budgetary CHP plant construction cost estimates are overly optimistic, prospec-
             tive CHP plant owners waste valuable time and capital resources on construction
             documents that will have to be abandoned when contractor bids are received. On the
             other hand, overly conservative budgetary construction cost estimates produced at the
   274   275   276   277   278   279   280   281   282   283   284