Page 36 - Sustainable On-Site CHP Systems Design, Construction, and Operations
P. 36

Overview    15


                 •  Store excess thermal production as heat when the power demand exceeds the
                    heat demand; either cool or heat storage must be able to productively discharge
                    most of its energy before it is dissipated to the environment.
                 •  Sell excess power or heat through approved paralleling protocols on a mutually
                    acceptable contract basis to a user outside of the host facility (off-site). Often the
                    buyer is the local utility, but sometimes it is nearby or “over the fence.”


             Quality of Heat
             The quality (temperature and pressure) of recovered energy needed by the facility is
             another major determinant in selecting the prime mover. If high-pressure steam is
             required using a topping-cycle, the only option is to use a CTG with a HRSG.


             General System Sizing
             As discussed in this book, proper CHP system sizing is critical to the sustainability of a
             CHP system. For example, if a CHP system is oversized, it is likely that the facility will
             not fully be able to utilize the waste heat, heat dumping will occur, overall system
             efficiencies will be low, and economic expectations may not be realized. If a CHP system
             is undersized electric and thermal loads may not be served and economic opportunities
             will be forgone, for example.
                Note that CHP systems fall into two process categories:
                  1. Topping-cycle. A CHP process in which the energy input to the system is first
                    used to produce useful power output, and at least some of the rejected heat
                    from the power production process is then used to provide useful thermal
                    energy to the facilities.
                  2. Bottoming-cycle. A CHP process in which the energy input to the system is first
                    applied to produce useful thermal energy, and at least some of the rejected heat
                    emerging from the thermal application is then used for power production.

                Bottoming-cycles are typically used for facilities or industries that are heat load
             driven. That is, facilities that typically require large amounts of heat for their process.
             The topping-cycle has several variations and can be sized to meet the following:
                 •  A portion of the facilities electric load (peaking plant)
                 •  The facilities base electric load
                 •  The facilities total peak electric load
                 •  A portion of the facilities thermal load
                 •  The facilities base thermal load
                 •  The facilities peak thermal load
                Unless power or thermal energy is to be exported from the site, the sizing variations
             listed above sets the “edges of the envelope” with respect to CHP plant size, and as
             discussed in Chap. 8 the various options need to be carefully studied. For example, a
             CHP plant sized to meet the peak electric demand provides maximum energy cost
             savings and maximum reliability, but may be large and relatively expensive to con-
             struct. Further, for many of the hours in a year, the peak demand cogeneration system
   31   32   33   34   35   36   37   38   39   40   41