Page 95 - The Six Sigma Project Planner
P. 95
Risk Response Planning
Risk response plans should be prepared for those risk events identified as having a high
likelihood/impact profile. The tools shown in Table 5. Risk Response Planning Tools
can help the team with risk response planning. In addition, the team should also review
the results of its risk assessment for risk planning ideas. Risk assessments show the
team where the risk “lever points” are. Response plans can take advantage of this
information by indicating where the team should focus its response.
Table 5. Risk Response Planning Tools
27
Risk Response Planning Tool
Force Field Analysis
Process decision program charts
FMEA
27
Six Sigma Handbook, Chapters 8 and 16.
78