Risk Response Planning
                    Risk response plans should be prepared for those risk events identified as having a high
                    likelihood/impact profile. The tools shown in Table 5. Risk Response Planning Tools
                    can help the team with risk response planning. In addition, the team should also review
                    the results of its risk assessment for risk planning ideas. Risk assessments show the
                    team where the risk “lever points” are. Response plans can take advantage of this
                    information by indicating where the team should focus its response.
                                            Table 5. Risk Response Planning Tools

                                                                           27
                                                 Risk Response Planning Tool
                                        Force Field Analysis
                                        Process decision program charts
                                        FMEA













































                    27
                      Six Sigma Handbook, Chapters 8 and 16.