Page 115 - The Toyota Way Fieldbook
P. 115

92                        THE TOYOTA WAY FIELDBOOK



                Case Study: The Danger of Single-Piece Flow for Short
                Cycle-Time Jobs

                The move to making material flow from traditional “batch and queue”
                methods has become somewhat of a fad. As with most fads, they can be
                taken to an extreme, and negative consequences ensue. The single-piece
                flow “fad” has, in many cases created reduced performance results.
                Single-piece flow may not be the most efficient method for short cycle-
                time operations (30 seconds or less).
                A kaizen workshop was held with the objective of establishing single-
                piece flow capability in the assembly operation. The product was an
                assembled fitting requiring 13 seconds to complete. The takt time was
                determined to be 5 seconds, based on the customer demand. The
                work was divided among three operators, and a work cell (another
                fad) was created to facilitate the passing of product between operators,
                which is necessary for flow.

                Several months later this work area was struggling to meet the customer
                demand, and operators had returned to batching product between
                operations. Observation revealed two major issues. First, as the cycle
                balance chart in Figure 5-2 shows, the cycle times for the operators were
                not well balanced.
                This imbalance in work cycle times is a major reason operators begin
                to deviate from the “no batching” rule. When operators deviate from
                the original plan, it’s a strong indication that there is a flaw in the plan.
                Unfortunately, a struggle usually ensues as management attempts to
                enforce the rules of flow rather than to stop and consider where the



                     Cycle balance chart: Fitting assembly


                6                                   Takt time = 5 seconds
                5
              Seconds  3
                4
                2
                1
                0
                       Operator 1        Operator 2         Operator 3


         Figure 5-2. Original cycle balance chart for fitting assembly
   110   111   112   113   114   115   116   117   118   119   120