Page 158 -
P. 158

7: The Need for Standard IT Energy-Use Metrics                 123



                  ♦ Compute, network, and storage nodes.
                  ♦ Other miscellaneous component loads such as data center lighting.
                The PUE and DCiE provide a way to determine opportunities to

             ■ Improve a data center’s operational efficiency.
             ■ Compare a data center with competitive data centers.
             ■ Assess data center operators’ design and process improvements over time.
             ■ Repurpose energy for additional IT equipment.

                Although both of these metrics are essentially the same, you can use them
             to illustrate the energy allocation in the data center differently. For example,
             if a PUE is determined to be 3.0, this indicates that the data center demand
             is three times greater than the energy necessary to power the IT equipment.
             In addition, you can use the ratio as a multiplier for calculating the real
             impact of the system’s power demands. For example, if a server demands 500
             watts and the PUE for the data center is 3.0, then the power from the utility
             grid needed to deliver 500 watts to the server is 1,500 watts. DCiE is quite
                                                                                                               ptg
             useful as well. A DCiE value of 33 percent (equivalent to a PUE of 3.0) sug-
             gests that the IT equipment consumes 33 percent of the power in the data
             center.
                Total Facility Power is measured at or near the facility utility’s meters to
             accurately reflect the power entering the data center. This reading should
             represent the total power consumed in the data center. The data center-only
             portion of a building utility meter should be measured because power not
             intended for consumption in the data center can result in faulty PUE and
             DCiE metrics. For example, if a data center is in an office building, total
             power drawn from the utility is the sum of the Total Facility Power for the
             data center, plus the total power consumed by the nondata center offices.
                In such a case, the data center administrator needs to measure or estimate
             the amount of power consumed by the nondata center offices. An estimate
             will obviously introduce some error into the calculations. IT Equipment
             Power will be measured after all power conversion, switching, and condition-
             ing is completed and before the IT equipment itself. The most likely meas-
             urement point would be at the output of the computer room  power
             distribution units (PDUs). This measurement should represent the total
             power delivered to the computer equipment racks in the data center.
                The PUE can range from 1.0 to infinity. Ideally, a PUE value approaching
             1.0 would indicate 100 percent-efficiency (that is, all power used by IT
   153   154   155   156   157   158   159   160   161   162   163