Page 407 - Trenchless Technology Piping Installation and Inspection
P. 407

Inspection and QA/QC for Trenchless Installation and Replacement Methods   357



         Verify HDPE pipe is supported and secured reasonably with rollers, skates, or other
         protective devices to prevent damage to the pipe, is new with smooth interior and
         exterior surfaces, is used within the entire influence area of the roadbed, has clean
         and square ends, joints are butt-fused and watertight, pipe with gouges exceeding 10
         percent of the pipe wall thickness or kinked sections is not used, and damaged pipe is
         removed, and the host pipe is inspected with CCTV, and the bursting head diameter is
         comparable with the replacement pipe diameter.

         Verify sufficient lubrication fluid quantity is used, and a lubrication system properly
         injects lubricant on the inside and outside of the pipe.

         Verify any unsuccessful borehole is backfilled immediately.
         Verify each end of the pipe is enclosed, restoration is completed, and attach
         Inspector’s Daily Report (IDR), form 2228.

      Permit No. __________________________
      Inspector: ___________________________
      Date: _______________________________


     FIGURE 8.25  Sample checklist for inspection of pipe-replacement operations.
     (Continued)



     8.8  Access Pits/Driving and Receiving Shafts
             1.  Location: The location of drive and receiving shafts must be
                 proposed (submitted) by the contractors and approved by
                 the design engineer or the state DOT/agency/municipal-
                 ity based on approved guidelines and regulations and
                 project and site requirements. For example, Michigan DOT
                 requires a minimum distance of 20 ft, from the edge of the
                 paved shoulder or curb to the face of any shaft, equipment,
                 and supplies must be maintained in areas posted at 45 mph
                 or less; otherwise, a minimum distance of 30 ft must be
                 maintained.
             2.  Sheeting and bracing: Sheeting and bracing may be required
                 whenever any part of the shaft excavation is located within
                 the roadbed influence area. For example, an additional earth-
                 retention structure may be required above and below the
                 borehole on the boring face of all shafts to prevent loss of
                 road embankment materials during construction.
             3.  Surface and groundwater flow: Ground surface around shafts
                 and pits must be sloped away so surface runoff moves away
                 from shafts and pits. To remove any storm or groundwater
                 from shafts and pits, a sump pump must be installed at a pit
                 at the bottom of the shaft.
   402   403   404   405   406   407   408   409   410   411   412