Page 408 - Trenchless Technology Piping Installation and Inspection
P. 408

358     Cha pte r  Ei g h t

             4.  Protection:
                 •  Traffic barriers must be installed adjacent to shaft loca-
                   tions according to the state DOT or an agency having
                   jurisdiction or according to the standard specifications for
                   construction. Temporary beam guardrail must also be
                   installed according to the current DOT or agency having
                   jurisdiction or construction specifications.
                 •  Fencing barriers must be installed adjacent to shafts, open
                   excavations, equipment and supplies with suitable fenc-
                   ing and plastic drums to prohibit pedestrian access to the
                   work site. Equipment must not be used as fencing to pro-
                   tect shafts and pits.
                 •  The contractor must construct and operate safe access
                   shafts and pits according to OSHA guidelines and/or all
                   applicable regulatory requirements.



     8.9 Settlement/Heaving Monitoring

              1.  This method must be performed in a manner that will min-
                 imize the movement of the ground in front of, above, and
                 surrounding the boring operation, and will minimize
                 subsidence of the surface above and in the vicinity of the
                 boring.
              2.  Potential settlement must be monitored at each edge of right-
                 of-way, each shoulder point, each edge of pavement, the edge
                 of each lane (or centerline for two lane roads), and otherwise
                 at 50-ft intervals along the pipe centerline.
               3.  A survey must be performed 1 day prior to initiating this
                 operation at each required monitoring location. A similar sur-
                 vey must then be performed at each location, on a daily basis,
                 until the permitted activity has received a final inspection.
                 This survey establishes the preexisting and postconstruction
                 conditions, and the amount of settlement. All survey read-
                 ings must be recorded to the nearest one-hundredth (0.01) of
                 a foot. Whenever possible, trenchless pipe installations must
                 not be installed directly under a pavement crack. Digital pho-
                 tographs of the pavement conditions must also be taken prior
                 and after the pipe installation.
              4.  All operations must stop immediately whenever monitored
                 points indicate a vertical change in elevation of 1 in. or more,
                 or any surface disruption is observed. The contractor must
                 then immediately report the amount of settlement to the
                 engineer/inspector.
   403   404   405   406   407   408   409   410   411   412   413