Page 246 - Urban Construction Project Management
P. 246

Contracts  201
           5. Liquidated damages or consequential damages
             • The contractor is usually better off with a specified sum for each day lost than
               having to determine what the cost expenses might be at some future date.
             • The schedule has to be clearly defined.
             • Achange initiated by the owner must be detailed as to the possible extension of time.
             • Never agree to any consequential damages. They may include items by the owner
               that would be completely out of the scope of the project. If it cannot be avoided,
               then a list of all the consequential damages (with the costs) must be enumerated.
               The contractor should review this and unreasonable items should be eliminated.
           6. Force majeure
             • Events or circumstances beyond the control of the parties. Examples could be
               war, flooding, earthquakes, tornados, hurricanes, and volcano eruption.
             • Force majeure clause must be part of the contract. Thus, weather information
               history for the area in question must be analyzed.
           7. No damages for delay (by the owner)
             • This is an onerous contract provision and should be deleted. It typically states
               that the contractor’s sole and exclusive remedy, if delayed, is a time extension.
               The CM/GC should be paid for any event precipitated by the owner that will
               cause the project schedule to extend beyond the original agreed upon date.
             • Any delay caused by the owner will cause extensive costs to the CM/GC. This
               could be additional general conditions, subcontractor costs, and potential infla-
               tionary costs for material and labor.
           8. Warranty
             • Warranty for construction is usually for 1 year (except for certain work and equip-
               ment that may have an extended warranty).
             • When does the warranty period start? AIA documents state that the warranty
               period will start from substantial completion of the project.
             • Substantial completion as defined by the AIA is the period when the facility can
               be occupied for the owner’s beneficial use.
             • If the owner should occupy the space prior to substantial completion, then the
               responsibility of the owner must be detailed in writing as to the owner’s obliga-
               tion for non-completed areas. This could include protection of the walls, ceiling,
               and flooring; rebalancing of the mechanical systems; and early start-up costs for
               all systems.
             • Make sure that any warranty does not include maintenance of the equipment dur-
               ing the period unless expressly requested in the design documents.
             • If the owner wants the CM/GC to attend any meetings after the warranty period,
               then define the meetings and how the CM/GC will be paid.
           9. Allowances
             • When documents are presented that are not complete, an allowance must be
               indicated.
             • Make sure that any allowance is based on as much information as possible pro-
               vided by the design team.
   241   242   243   244   245   246   247   248   249   250   251