Page 50 - Urban Construction Project Management
P. 50

Risk Assessment and Problem Solving  25
           7. Controlling claims and litigation
           8. Risk management plan
           9. Risk avoidance and mitigation
          10. Risk transfer


          Categories of Risk
          Risks are sometimes broken down into three categories depending on their size and fre-
          quency as follows:
          1. Small, reoccurring, routine risk. These risks taken together usually pose no signifi-
            cant financial impact and the costs associated with them are absorbed by the CM/GC
            or the project budget contingency and loss control procedures. An example of this
            might be stolen small tools from the project site.
          2. Accidental risk. These are usually small in number, but large in cost, both individu-
            ally and taken together. These are usually covered by insurance and loss control
            procedures. An example of this might be a pedestrian being struck by some con-
            struction material while walking by the site.
          3. Catastrophic risk. These risks are usually small in number, but could have significant
            impact on the CM/GC and/or project, depending on the company’s liquidity, retained
            earnings, profitability, and level and types of insurance coverage. An example of a
            catastrophic risk is a building catching fire during the construction process, or a tower
            crane collapsing during the construction process.



          RISKS ENCOUNTERED DURING
          THE PROJECT LIFE CYCLE


          During the life cycle of the project it is likely that new risks may be encountered that
          had not been previously identified. Exhibit 2-4 is a sample list of such risks.

          After a new project risk has been identified, the member of the project team who
          identified the risk should raise the issue to the person on the project team responsible
          for risk management, usually the project manager (PM). The PM should then review
          the risk to determine its validity and level of priority. The PM should then take the
          appropriate action to resolve the issue, if that action is within their capabilities. These
          actions are:

          1. Identify and evaluate the risks.
          2. Complete risk assessment form and log them into the risk management log.
          3. Investigate project risks and develop alternative approaches.
          4. Assess impact on cost, schedule, and project logistics.
          5. Assess if there is any governing code considerations.
          6. Obtain approval of the owner.
   45   46   47   48   49   50   51   52   53   54   55