GENERAL WATER SUPPLY DESIGN CONSIDERATIONS 2-37

          TABLE 2-17
          Secondary maximum contaminant levels
          Contaminant                SMCL, mg/L a
          Chloride                      250
          Color                          15 color units
          Copper                          1
          Corrosivity                Noncorrosive
          Foaming agents                  0.5
          Hydrogen sulfide                0.05
          Iron                            0.3
          Manganese                       0.05
          Odor                            3 threshold odor number units
          pH                              6.5–8.5
          Sulfate                       250
          Total dissolved solids (TDS)  500
          Zinc                            5

          a
          All quantities are mg/L except those for which units are given.


              Secondary Maximum Contaminant Levels (SMCLs).   The National Safe Drinking Water
          Act also provided for the establishment of an additional set of standards to prescribe maximum
           limits for those contaminants that tend to make water disagreeable to use, but that do not have
          any particular adverse public health effect. These secondary maximum contaminant levels are
          the advisable maximum level of a contaminant in any public water supply system. The levels are
          shown in  Table 2-17 .

             AWWA Goals.  The primary and secondary maximum contaminant levels are the maximum
          allowed (or recommended) values of the various contaminants. However, a reasonable goal may
          be much lower than the MCLs themselves. The American Water Works Association (AWWA)
          has issued its own set of goals to which its members try to adhere. These goals are shown in
           Table 2-18 .


                   2-4   EVALUATION OF PROCESS OPTIONS
            In the design process, the data gathered in the sections outlined to this point in the chapter would
          be sufficient to begin screening alternative supply and treatment options. In most cases a number
          of options will be available. The pros and cons of these selections are discussed in Chapters 3
          through 16.


              2-5   PLANT SIZING AND LAYOUT
           Once the preliminary selection of the water treatment unit operations and processes has been
          made (the screening process discussed in Chapter 1), rough calculations are made to determine
          sizes to be used in examining feasibility of site locations and cost. The elements to be considered