Page 504 - Moving the Earth_ The Workbook of Excavation
P. 504

PIT OPERATION


                   10.10  THE WORK







































                                        FIGURE 10.10  Overburden removed with dragline and shovel.


                                 Very large draglines may be able to dig solid shale, but not sandstone. In such formations only
                               the sandstone layers would need to be drilled and blasted.

                               Grading Spoil.  The spoil banks from light stripping operations can be leveled by bulldozers,
                               scrapers, or graders. However, the huge machines used in heavy stripping leave such large, coarse
                               piles that the biggest dozers cannot reduce them economically.
                                 The problem is largely a new one, as prior to legislation of the subject, most of the stripped
                               areas were left as permanent wastelands.
                                 If a front shovel is moved short distances frequently, the high peaks of its spoil ridge are greatly
                               reduced, as indicated between Fig. 10.11(A) and (B). The more even ridge top is the more readily
                               broken down by a bulldozer working along its crest.
                                 If the boom and stick are longer than required by the height and slope of the bank, the ridge
                               and trough surface can be eliminated by building out level with the old bank, (D) and (E), instead
                               of heaping toward the pit, as in (C). Accurate grading cannot be expected in such overhead dump-
                               ing, but the bulk of the irregularities can be eliminated.
                                 A dragline with extra boom length can build a flat-top pile by dumping against the bank near
                               the top at full reach, and building out the edge by shorter or longer swings as required.
                               Approximately the same result can be obtained with a slightly shorter boom by throwing some
                               spoil.
                                 Another dragline procedure, requiring extra clearance at the pile foot, is to drag the top of the
                               completed pile onto the slope to the pit, as in (F) and (G).
   499   500   501   502   503   504   505   506   507   508   509