Page 45 -
P. 45

3.10                       CHAPTER THREE


         mitted for owner review. In addition, they must accompany applications for state or fed-
         eral funding assistance.

         Bid Documents.  Final design plans and specifications  can be formatted to allow  con-
         struction using one of several contracting approaches.  Normally, conventional bid docu-
         ments are used that allow the owner to accept competitive bids and award the entire con-
         struction job, or job components, to the  lowest qualified, responsible bidder.  Under this
         approach  all elements shown in the bid documents are  the contractor's responsibility to
         construct,  with the owner and engineer inspecting the project to ensure compliance with
         bid documents. In some instances, major equipment to be installed on the project is pre-
         purchased by the owner and supplied to the contractor for installation. Prepurchased  equip-
         ment is normally used to accelerate  the construction schedule  or to allow use of propri-
         etary  equipment.
           Another bid approach  gaining popularity is use of a "design-build" format. Under this
         approach,  only preliminary engineering is completed for bidding, with final design pre-
         pared by the lowest, qualified, responsible bidder.  The owner then monitors compliance
         with bid documents during construction, usually with assistance  from the preliminary de-
         signer.  The primary benefit of the  design-build approach  is the single source of respon-
         sibility provided to  the  owner,  allowing a  single point of contact for  design and con-
         struction issues.  Combining design and construction responsibilities provides  a  greater
         potential to  shorten the  project  implementation period by overlapping design and con-
         struction.  One of the  primary concerns with  using design-build is  the  possible  loss  of
         checks  and balances between the  designer and contractor,  which is provided by the tra-
         ditional contractual separation between both parties.



         CONSTRUCTION ASSISTANCE

         After completion of final design and incorporation of all pertinent review comments,  the
         water  treatment plant design can proceed  into the  construction phase.  During construc-
         tion of water treatment plant facilities,  a number of design issues must be addressed  to
         ensure the successful  implementation of the contract documents. These relate  to bid ad-
         ministration, construction administration, design disciplines coordination, and owner and
         regulatory review of change orders.


         Bid  Administration
         The time flame required for bidding varies  depending on the size and complexity of the
         project but is  normally about 30  to  60 days.  Bid administration activities generally  in-
         clude printing the  bid documents, conducting prebid meetings, answering bidder ques-
         tions,  preparing addenda to  bid documents, bid evaluation and award  recommendation,
         and contract preparation.  Bid administration concludes with the award of the construction
        contract and the issuance of a notice to proceed  to the selected  contractor.


        Construction  Administration
        The administration of project construction consists of a number of tasks that must be pro-
        vided to oversee the work in progress.  Some of the principal duties include
   40   41   42   43   44   45   46   47   48   49   50