Page 46 -
P. 46

DESIGN AND CONSTRUCTION                 3.11


         •  Field observation of the work as it progresses to verify the contractor's compliance with
          contract documents
         •  Clarification of contractor questions pertaining to the drawings and specifications
         •  Review of shop drawings submitted by the contractor
         •  Review of payment requests
         •  Monitoring compliance with the construction schedule
         •  Testing materials and systems for acceptability
         •  Coordination of field orders and change orders

           Timely and relevant communication between all parties  involved in the construction
         of the plant improvements is critical to the success of the project. On larger or more com-
         plex  projects,  formal  "partnering" is  sometimes utilized to facilitate communication be-
         tween all parties and to minimize conflicts.



         Coordination  of Design  Disciplines
         All design disciplines should be  actively involved in construction administration. Mem-
        bers  of the  design  team  should make  periodic  visits to  the  construction site to  monitor
         construction activities related to  their discipline. As  part  of plant construction adminis-
        tration, it is necessary to coordinate modifications and changes to design with the various
        design disciplines.


        Construction  Approvals
        No matter how carefully a construction job is planned and designed, there are almost al-
         ways some changes that must be made during construction as a result of unexpected prob-
        lems or a change of mind by the owner, designer, or regulatory agency.
         Owner Approval of Change Orders.  To facilitate timely processing of changes to con-
        tract documents, the owner should be apprised of potential or upcoming change orders as
         they become apparent.  Owner approval is normally required for most change orders un-
         less the designer has been designated as the client's contractual authority. Documentation
         should be provided  for  each  change  order  to  ensure that  all parties  have  a  clear under-
         standing of the changes it will cause in the project cost and construction schedule.
        Regulatory Approval of Change Orders.  In  many  instances  in  which  regulatory  ap-
         proval of the design has been obtained, change orders must be approved by the agencies
         to ensure that the project  still complies with  agency regulations. Regulatory  approval of
         change orders may also be necessary when funding for construction is provided by a reg-
         ulatory agency.


         Facilities  Start-up

         The final phase of a water treatment plant construction project involves activities associ-
         ated  with  start-up and initial operation of the new facilities. The  contractor is normally
         required to organize and conduct the start-up of new plant facilities, with the owner and
         designer overseeing the activities.
   41   42   43   44   45   46   47   48   49   50   51