5 - PROJECT SCOPE MANAGEMENT






                         Completion of the project scope is measured against the project management plan (Section 4.2.3.1). Completion
                      of the product scope is measured against the product requirements (Section 5.2). The Project Scope Management
                      processes need to be well integrated with the other Knowledge Area processes, so that the work of the project will
                      result in delivery of the specified product scope.

                                                            Project Scope Management
                                                                   Overview


                                       5.1 Plan Scope             5.2 Collect             5.3 Define Scope
                                       Management                Requirements
                                  .1  Inputs                .1  Inputs                 .1  Inputs
                                     .1  Project management plan     .1  Scope management plan     .1  Scope management plan
                                     .2  Project charter       .2  Requirements management       .2  Project charter
                                     .3  Enterprise environmental    plan                 .3  Requirements documentation
                                      factors                  .3  Stakeholder management plan     .4  Organizational process assets
                                     .4  Organizational process assets     .4  Project charter
                                                               .5  Stakeholder register  .2  Tools & Techniques
                                  .2  Tools & Techniques                                  .1  Expert judgment
                                     .1  Expert judgment    .2  Tools & Techniques        .2  Product analysis
                                     .2  Meetings              .1  Interviews             .3  Alternatives generation
                                                               .2  Focus groups           .4  Facilitated workshops
                                   .3 Outputs                  .3  Facilitated workshops
                                     .1  Scope management plan     .4  Group creativity techniques   .3 Outputs
                                     .2  Requirements management       .5  Group decision-making       .1  Project scope statement
                                      plan                      techniques                .2  Project documents updates
                                                               .6  Questionnaires and surveys
                                                               .7  Observations
                                                               .8  Prototypes
                                      5.4 Create WBS           .9  Benchmarking           5.6 Control Scope
                                                                .10  Context diagrams
                                                                .11  Document analysis
                                  .1  Inputs                                           .1  Inputs
                                     .1  Scope management plan   .3 Outputs               .1  Project management plan
                                     .2  Project scope statement     .1  Requirements documentation     .2  Requirements documentation
                                     .3  Requirements documentation     .2  Requirements traceability       .3  Requirements traceability
                                     .4  Enterprise environmental     matrix              matrix
                                       factors                                            .4  Work performance data
                                     .5  Organizational process                           .5  Organizational process assets
                                      assets
                                                               5.5 Validate Scope      .2  Tools & Techniques
                                  .2  Tools & Techniques                                  .1  Variance analysis
                                     .1  Decomposition
                                     .2  Expert judgment    .1  Inputs                 .3  Outputs
                                                               .1  Project management plan     .1  Work performance
                                  .3  Outputs                  .2  Requirements documentation  information
                                     .1  Scope baseline        .3  Requirements traceability       .2  Change requests
                                     .2  Project documents updates  matrix                .3  Project management plan
                                                               .4  Verified deliverables  updates
                                                               .5  Work performance data     .4  Project documents updates
                                                                                          .5  Organizational process assets
                                                            .2  Tools & Techniques        updates
                                                               .1  Inspection
                                                               .2  Group decision-making
                                                                techniques
                                                            .3  Outputs
                                                               .1  Accepted deliverables
                                                               .2  Change requests
                                                               .3  Work performance information
                                                               .4  Project documents updates

                                                Figure 5-1. Project Scope Management overview







             106      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   127   128   129   130   131   132   133   134   135   136   137