Page 215 -
P. 215

6 - PROJECT TIME MANAGEMENT






                        •   critical chain method (Section 6.6.2.3). Comparing the amount of buffer remaining to the amount of
                           buffer needed to protect the delivery date can help determine schedule status. The difference between
                           the buffer needed and the buffer remaining can determine whether corrective action is appropriate.
                        •   Earned value management (Section 7.4.2.1). Schedule performance measurements such as schedule
                           variance (SV) and schedule performance index (SPI), are used to assess the magnitude of variation to the
                           original schedule baseline. The total float and early finish variances are also essential planning components
                           to evaluate project time performance. Important aspects of schedule control include determining the cause
                           and degree of variance relative to the schedule baseline (Section 6.6.3.1), estimating the implications
                           of those variances for future work to completion, and deciding whether corrective or preventive action   6
                           is required. For example, a major delay on any activity not on the critical path may have little effect on
                           the overall project schedule, while a much shorter delay on a critical or near-critical activity may require
                           immediate action. For projects not using earned value management, similar variance analysis can be
                           performed by comparing planned activity start or finish dates against actual start or finish dates to
                           identify variances between the schedule baseline and actual project performance. Further analysis can
                           be performed to determine the cause and degree of variance relative to the schedule baseline and any
                           corrective or preventative actions needed.


                   6.7.2.2 Project Management Software

                     Project management software for scheduling provides the ability to track planned dates versus actual dates,
                   to report variances to and progress made against the schedule baseline, and to forecast the effects of changes
                   to the project schedule model.



                   6.7.2.3 resource optimization techniques

                     Described in Section 6.6.2.4. Resource optimization techniques involve the scheduling of activities and the
                   resources required by those activities while taking into consideration both the resource availability and the project
                   time.


                   6.7.2.4 Modeling techniques

                     Described in Section 6.6.2.5. Modeling techniques are used to review various scenarios guided by risk monitoring
                   to bring the schedule model into alignment with the project management plan and approved baseline.


















                                                                                       ®
                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   189


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   210   211   212   213   214   215   216   217   218   219   220