6 - PROJECT TIME MANAGEMENT
Project Time Management
6.6
4.3 Develop
Direct and Schedule Project
Manage Project Documents
Work • Project schedule
• Project calendars
• Schedule data
• Work • Project
performance documents
data updates
6.7 4.4
Control Monitor and
• Project Schedule • Schedule forecasts Control Project
Work
management • Organizational • Work performance
plan process assets information
4.2
Develop Project 4.5
Management • Change requests Perform
Plan Integrated
• Project Change Control
management plan
updates
Enterprise/
Organization
• Organizational
process assets updates
Figure 6-23. control Schedule data Flow diagram
Updating the schedule model requires knowing the actual performance to date. Any change to the schedule
baseline can only be approved through the Perform Integrated Change Control process (Section 4.5). Control
Schedule, as a component of the Perform Integrated Change Control process, is concerned with:
• Determining the current status of the project schedule,
• Influencing the factors that create schedule changes,
• Determining if the project schedule has changed, and
• Managing the actual changes as they occur.
186 ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide) – Fifth Edition
®
Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
This copy is a PMI Member benefit, not for distribution, sale, or reproduction.