Page 211 -
P. 211

6 - PROJECT TIME MANAGEMENT






                   6.6.3.6 Project documents updates

                     Project documents that may be updated include, but are not limited to:

                        •   Activity resource requirements. Resource leveling can have a significant effect on preliminary estimates
                           for the types and quantities of resources required. If the resource-leveling analysis changes the project
                           resource requirements, then the project resource requirements are updated.
                        •   Activity attributes. Activity attributes (Section 6.2.3.2) are updated to include any revised resource
                           requirements and any other revisions generated by the Develop Schedule process.
                        •   calendars. The calendar for each project may consist of multiple calendars, project calendars, individual   6
                           resource calendars etc., as the basis for scheduling the project.

                        •   risk register. The risk register may need to be updated to reflect opportunities or threats perceived
                           through scheduling assumptions.


                   6.7 control Schedule


                     Control Schedule is the process of monitoring the status of project activities to update project progress and
                   manage changes to the schedule baseline to achieve the plan. The key benefit of this process is that it provides
                   the means to recognize deviation from the plan and take corrective and preventive actions and thus minimize
                   risk. The inputs, tools and techniques, and outputs of this process are depicted in Figure 6-22. Figure 6-23
                   depicts the data flow diagram of the process.


                                     Inputs            Tools & Techniques           Outputs

                              .1  Project management plan  .1  Performance reviews  .1  Work performance
                              .2  Project schedule    .2  Project management      information
                              .3  Work performance data    software           .2  Schedule forecasts
                              .4  Project calendars   .3  Resource optimization    .3  Change requests
                              .5  Schedule data         techniques            .4  Project management plan
                              .6  Organizational process    .4  Modeling techniques   updates
                                assets                .5  Leads and lags      .5  Project documents
                                                      .6  Schedule compression   updates
                                                      .7  Scheduling tool     .6  Organizational process
                                                                               assets updates


                                   Figure 6-22. control Schedule: Inputs, tools & techniques, and outputs



















                                                                                       ®
                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   185


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   206   207   208   209   210   211   212   213   214   215   216