6 - PROJECT TIME MANAGEMENT
Milestone Schedule
Project Schedule Time Frame
Activity Calendar
Identifier Activity Description units Period 1 Period 2 Period 3 Period 4 Period 5
1.1.MB Begin New Product Z 0
1.1.1.M1 Complete Component 1 0
1.1.2.M1 Complete Component 2 0
1.1.3.M1 Complete Integration of Components 1 & 2 0
1.1.3.MF Finish New Product Z 0
6
Data Date
Summary Schedule
Activity Calendar Project Schedule Time Frame
Identifier Activity Description units Period 1 Period 2 Period 3 Period 4 Period 5
1.1 Develop and Deliver New Product Z 120
1.1.1 Work Package 1: Component 1 67
1.1.2 Work Package 2: Component 2 53
1.1.3 Work Package 3: Integrated Components 1 and 2 53
Data Date
Detailed Schedule
Activity Calendar Project Schedule Time Frame
Identifier Activity Description units Period 1 Period 2 Period 3 Period 4 Period 5
1.1.MB Begin New Product Z 0
1.1 Develop and Deliver Product Z 120
1.1.1 Work Package 1: Component 1 67
1.1.1.D Design Component 1 20 FS
1.1.1.B Build Component 1 33
1.1.1.T Test Component 1 14
SS
1.1.1.M1 Complete Component 1 0
1.1.2 Work Package 2: Component 2 53
1.1.2.D Design Component 2 14
1.1.2.B Build Component 2 28
1.1.2.T Test Component 2 11
1.1.2.M1 Complete Component 2 0
1.1.3 Work Package 3: Integrated Components 1 and 2 53
1.1.3.G Integrate Components 1 and 2 as Product Z 14
1.1.3.T Complete Integration of Components 1 and 2 32
1.1.3.M1 Test Integrated Components as Product Z 0
1.1.3.P Deliver Product Z 7
1.1.3.MF Finish New Product Z 0
Data Date
Figure 6-21. Project Schedule Presentations —Examples
©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide) – Fifth Edition 183
®
Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
This copy is a PMI Member benefit, not for distribution, sale, or reproduction.