7 - PROJECT COST MANAGEMENT











                                       4.1
                                    Develop Project         Project Cost Management
                                      Charter
                                         • Project charter
                                                                     7.1
                                                                   Plan Cost
                                         • Project                 Management
                                           management   • Enterprise
                                           plan       environmental
                                                       factors
                                       4.2           • Organizational   • Cost
                                    Develop Project    process assets    management
                                    Management                           plan                      11.2
                                       Plan                                                       Identify
                                                                                                  Risks
                                                           6.2
                                                           Define
                                                          Activities
                                     Enterprise/                                                  11.4
                                     Organization                                                 Perform
                                                                                                Quantitative
                                                           6.3                                  Risk Analysis
                                                          Sequence
                                                          Activities



                                             Figure 7-3. Plan cost Management: data Flow diagram


                         The cost management processes and their associated tools and techniques are documented in the cost
                      management plan. The cost management plan is a component of the project management plan.



                      7.1.1 Plan cost Management: Inputs



                      7.1.1.1 Project Management Plan

                         Described in Section 4.2.3.1. The project management plan contains information used to develop the cost
                      management plan, which contains, but is not limited to:

                            •   Scope  baseline.  The  scope  baseline includes the project  scope  statement  and WBS  detail  for  cost
                              estimation and management.

                            •  Schedule baseline. The schedule baseline defines when the project costs will be incurred.
                            •   other information. Other cost-related scheduling, risk, and communications decisions from the project
                              management plan.












             196      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   217   218   219   220   221   222   223   224   225   226   227