7 - PROJECT COST MANAGEMENT











                                                         Project Cost Management
                                    5.4                                                       Project
                                   Create                                                    Documents
                                   WBS                            7.1
                                                                Plan Cost
                                                               Management
                                    6.6
                                   Develop                         • Cost
                                  Schedule                           management                 6.4
                                                                     plan                    Estimate Activity
                                  • Project schedule                                          Resources
                                                 • Scope baseline          • Project documents
                                    9.1                                      updates                                      7
                                 Plan Human                       7.2                           11.2
                                  Resource                      Estimate                       Identify
                                 Management                      Costs       • Activity cost   Risks
                                                                               estimates
                                 • Human resource
                                   management plan  • Enterprise
                                                  environmental
                                                   factors                                      12.1
                                    11.2         • Organizational   • Basis of              Plan Procurement
                                                                     estimates
                                   Identify        process assets                            Management
                                   Risks
                                 • Risk register
                                                                           7.3
                                                                         Determine
                                  Enterprise/                             Budget
                                 Organization




                                              Figure 7-5. Estimate costs data Flow diagram

                     Cost estimates are a prediction that is based on the information known at a given point in time. Cost estimates
                   include the identification and consideration of costing alternatives to initiate and complete the project. Cost trade-
                   offs and risks should be considered, such as make versus buy, buy versus lease, and the sharing of resources in
                   order to achieve optimal costs for the project.
                     Cost estimates are generally expressed in units of some currency (i.e., dollars, euros, yen, etc.), although in
                   some instances other units of measure, such as staff hours or staff days, are used to facilitate comparisons by
                   eliminating the effects of currency fluctuations.

                     Cost estimates should be reviewed and refined during the course of the project to reflect additional detail
                   as it becomes available and assumptions are tested. The accuracy of a project estimate will increase as the
                   project progresses through the project life cycle. For example, a project in the initiation phase may have a rough
                   order of magnitude (ROM) estimate in the range of −25% to +75%. Later in the project, as more information is
                   known, definitive estimates could narrow the range of accuracy to -5% to +10%. In some organizations, there are
                   guidelines for when such refinements can be made and the degree of confidence or accuracy that is expected.








                                                                                       ®
                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   201