Page 229 -
P. 229

7 - PROJECT COST MANAGEMENT






                     Additional information that may be found in the scope baseline with contractual and legal implications, such as
                   health, safety, security, performance, environmental, insurance, intellectual property rights, licenses, and permits.
                   All of this information should be considered when developing the cost estimates.


                   7.2.1.4 Project Schedule

                     Described in Section 6.6.3.2. The type and quantity of resources and the amount of time which those resources
                   are applied to complete the work of the project are major factors in determining the project cost. Schedule activity
                   resources and their respective durations are used as key inputs to this process. Estimate Activity Resources (Section
                   6.4) involves determining the availability of staff, the number of staff hours required, and quantities of material and
                   equipment needed to perform schedule activities. It is closely coordinated with cost estimating. Activity duration   7
                   estimates (Section 6.5.3.1) will affect cost estimates on any project where the project budget includes an allowance
                   for the cost of financing (including interest charges) and where resources are applied per unit of time for the
                   duration of the activity. Activity duration estimates can also affect cost estimates that have time-sensitive costs
                   included in them, such as union labor with regularly expiring collective bargaining agreements or materials with
                   seasonal cost variations.


                   7.2.1.5 risk register

                     Described in Section 11.2.3.1. The risk register should be reviewed to consider risk response costs. Risks,
                   which can be either threats or opportunities, typically have an impact on both activity and overall project costs. As
                   a general rule, when the project experiences a negative risk event, the near-term cost of the project will usually
                   increase, and there will sometimes be a delay in the project schedule. In a similar way, the project team should
                   be sensitive to potential opportunities that can benefit the business either by directly reducing activity costs or by
                   accelerating the schedule.


                   7.2.1.6 Enterprise Environmental Factors

                     Described in Section 2.1.5. The enterprise environmental factors that influence the Estimate Costs process
                   include, but are not limited to:

                        •   Market conditions. These conditions describe what products, services, and results are available in the
                           market, from whom, and under what terms and conditions. Regional and/or global supply and demand
                           conditions greatly influence resource costs.

















                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   203
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   224   225   226   227   228   229   230   231   232   233   234