Page 225 -
P. 225

7 - PROJECT COST MANAGEMENT






                     For example, the cost management plan can establish the following:

                        •   units of measure. Each unit used in measurements (such as staff hours, staff days, weeks for time
                           measures; or meters, liters, tons, kilometers, or cubic yards for quantity measures; or lump sum in
                           currency form) is defined for each of the resources.

                        •   Level of precision.  The degree to which activity cost estimates will be rounded up or down (e.g.,
                           US$100.49 to US$100, or US$995.59 to US$1,000), based on the scope of the activities and magnitude
                           of the project.
                        •   Level of accuracy. The acceptable range (e.g., ±10%) used in determining realistic activity cost estimates
                           is specified, and may include an amount for contingencies;
                        •   organizational procedures links.  The work breakdown structure (WBS) (Section 5.4) provides the   7
                           framework for the cost management plan, allowing for consistency with the estimates, budgets, and
                           control of costs. The WBS component used for the project cost accounting is called the control account.
                           Each control account is assigned a unique code or account number(s) that links directly to the performing
                           organization’s accounting system.
                        •   control thresholds. Variance thresholds for monitoring cost performance may be specified to indicate
                           an agreed-upon amount of variation to be allowed before some action needs to be taken. Thresholds are
                           typically expressed as percentage deviations from the baseline plan.
                        •   rules of performance measurement. Earned value management (EVM) rules of performance
                           measurement are set. For example, the cost management plan may:

                                   ○ Define the points in the WBS at which measurement of control accounts will be performed;
                                   ○  Establish the earned value measurement techniques (e.g., weighted milestones, fixed-formula,
                                   percent complete, etc.) to be employed; and
                                   ○  Specify tracking methodologies and the earned value management computation equations for
                                   calculating projected estimate at completion (EAC) forecasts to provide a validity check on the
                                   bottom-up EAC.

                           For more specific information regarding earned value management, refer to the Practice Standard for
                           Earned Value Management – Second Edition.























                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   199
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   220   221   222   223   224   225   226   227   228   229   230