7 - PROJECT COST MANAGEMENT
Project Cost Management
5.4
Create 7.1 7.2
WBS Plan Cost Estimate
Management Costs
Project
6.6 • Cost • Activity cost estimates Documents
Develop management • Basis of estimates
Schedule plan
• Project schedule • Scope baseline
• Project documents
updates
9.2 7.3 7
Acquire Project Determine 4.2
Team Budget Develop Project
• Cost baseline Management
• Resource calendars Plan
• Resource
calendars
11.2
Identify • Project
Risks funding
requirements
• Risk register
12.2 7.4
Conduct • Agreements Control
Procurements Costs
• Organizational
Enterprise/ process assets
Organization
Figure 7-7. determine Budget data Flow diagram
A project budget includes all the funds authorized to execute the project. The cost baseline is the approved
version of the time-phased project budget, but excludes management reserves.
7.3.1 determine Budget: Inputs
7.3.1.1 cost Management Plan
Described in Section 7.1.3.1. The cost management plan describes how the project costs will be managed and
controlled.
®
©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide) – Fifth Edition 209
Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
This copy is a PMI Member benefit, not for distribution, sale, or reproduction.