Page 239 -
P. 239

7 - PROJECT COST MANAGEMENT






                     Figure 7-8 illustrates the various components of the project budget and cost baseline. Activity cost estimates
                   for the various project activities along with any contingency reserves (Section 7.2.2.6) for these activities are
                   aggregated into their associated work package costs. The work package cost estimates, along with any contingency
                   reserves estimated for the work packages, are aggregated into control accounts. The summation of the control
                   accounts make up the cost baseline. Since the cost estimates that make up the cost baseline are directly tied to the
                   schedule activities, this enables a time-phased view of the cost baseline, which is typically displayed in the form of
                   an S-curve, as is illustrated in Figure 7-9.

                     Management reserves (Section 7.2.2.6) are added to the cost baseline to produce the project budget. As changes
                   warranting the use of management reserves arise, the change control process is used to obtain approval to move
                   the applicable management reserve funds into the cost baseline.
                                                                                                                          7




                                       Project    Management
                                       Budget      Reserve
                                                    Cost         Control    Contingency
                                                   Baseline     Accounts      Reserve
                                                                            Work Package   Activity
                                                                            Cost Estimates  Contingency Reserve
                                                                                         Activity Cost
                                                                                          Estimates
                                Total Amount









                                                          Project Budget Component


                                                 Figure 7-8. Project Budget components




























                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   213
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   234   235   236   237   238   239   240   241   242   243   244