7 - PROJECT COST MANAGEMENT






                      7.3.1.2 Scope Baseline

                           •   Project scope statement. Formal limitations by period for the expenditure of project funds can be
                              mandated by the organization, by agreement (Section 12.2.3.2), or by other entities such as government
                              agencies. These funding constraints are reflected in the project scope statement.
                           •   Work breakdown structure. The WBS (Section 5.4) provides the relationships among all the project
                              deliverables and their various components.
                           •   WBS dictionary. The WBS dictionary (Section 5.4.3.1) and related detailed statements of work provide
                              an identification of the deliverables and a description of the work in each WBS component required to
                              produce each deliverable.


                      7.3.1.3 Activity cost Estimates

                         Described in Section 7.2.3.1. Cost estimates for each activity within a work package are aggregated to obtain a
                      cost estimate for each work package.


                      7.3.1.4 Basis of Estimates

                         Described in Section 7.2.3.2. Supporting detail for cost estimates contained in the basis for estimates should
                      specify any basic assumptions dealing with the inclusion or exclusion of indirect or other costs in the project budget.


                      7.3.1.5 Project Schedule


                         Described in Section 6.6.3.2. The project schedule includes planned start and finish dates for the project’s
                      activities, milestones, work packages, and control accounts. This information can be used to aggregate costs to the
                      calendar periods in which the costs are planned to be incurred.


                      7.3.1.6 resource calendars

                         Described in Sections 9.2.3.2 and 12.2.3.3. Resource calendars provide information on which resources are
                      assigned to the project and when they are assigned. This information can be used to indicate resource costs over
                      the duration of the project.


                      7.3.1.7 risk register

                         Described in Section 11.2.3.1. The risk register should be reviewed to consider how to aggregate the risk response
                      costs. Updates to the risk register are included with project document updates described in Section 11.5.3.2.











             210      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   231   232   233   234   235   236   237   238   239   240   241