Page 336 -
P. 336

11 - PROJECT RISK MANAGEMENT






                         Project risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or
                      more project objectives such as scope, schedule, cost, and quality. A risk may have one or more causes and,
                      if it occurs, it may have one or more impacts. A cause may be a given or potential requirement, assumption,
                      constraint, or condition that creates the possibility of negative or positive outcomes. For example, causes could
                      include the requirement of an environmental permit to do work, or having limited personnel assigned to design the
                      project. The risk is that the permitting agency may take longer than planned to issue a permit; or, in the case of
                      an opportunity, additional development personnel may become available who can participate in design, and they
                      can be assigned to the project. If either of these uncertain events occurs, there may be an impact on the project,
                      scope, cost, schedule, quality, or performance. Risk conditions may include aspects of the project’s or organization’s
                      environment that contribute to project risk, such as immature project management practices, lack of integrated
                      management systems, concurrent multiple projects, or dependency on external participants who are outside the
                      project’s direct control.
                         Project risk has its origins in the uncertainty present in all projects. Known risks are those that have been
                      identified and analyzed, making it possible to plan responses for those risks. Known risks that cannot be managed
                      proactively, should be assigned a contingency reserve. Unknown risks cannot be managed proactively and therefore
                      may be assigned a management reserve. A negative project risk that has occurred is considered an issue.

                         Individual project risks  are  different from  overall project risk.  Overall  project  risk  represents  the  effect  of
                      uncertainty on the project as a whole. It is more than the sum of the individual risks within a project, since it includes
                      all sources of project uncertainty. It represents the exposure of stakeholders to the implications of variations in
                      project outcome, both positive and negative.

                         Organizations perceive risk as the effect of uncertainty on projects and organizational objectives. Organizations
                      and stakeholders are willing to accept varying degrees of risk depending on their risk attitude. The risk attitudes of
                      both the organization and the stakeholders may be influenced by a number of factors, which are broadly classified
                      into three themes:
































             310      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   331   332   333   334   335   336   337   338   339   340   341