11 - PROJECT RISK MANAGEMENT






                        •   Schedule management plan. The schedule management plan is updated to reflect changes in process
                           and practice driven by the risk responses. This may include changes in tolerance or behavior related to
                           resource loading and leveling, as well as updates to the schedule strategy.
                        •   cost management plan. The cost management plan is updated to reflect changes in process and
                           practice driven by the risk responses. This may include changes in tolerance or behavior related to
                           cost accounting, tracking, and reports, as well as updates to the budget strategy and how contingency
                           reserves are consumed.
                        •   Quality management plan. The quality management plan is updated to reflect changes in process
                           and practice driven by the risk responses. This may include changes in tolerance or behavior related to
                           requirements, quality assurance, or quality control, as well as updates to the requirements documentation.
                        •   Procurement management plan.  The procurement management plan may be updated to reflect
                           changes in strategy, such as alterations in the make-or-buy decision or contract type(s) driven by the risk
                           responses.

                        •   Human resource management plan. The staffing management plan, part of the human resource
                           management plan, is updated to reflect changes in project organizational structure and resource
                           applications driven by the risk responses. This may include changes in tolerance or behavior related to   11
                           staff allocation, as well as updates to the resource loading.

                        •   Scope baseline. Because of new, modified or omitted work generated by the risk responses, the scope
                           baseline may be updated to reflect those changes.

                        •   Schedule baseline. Because of new work (or omitted work) generated by the risk responses, the schedule
                           baseline may be updated to reflect those changes.
                        •   cost baseline. Because of new work (or omitted work) generated by the risk responses, the cost baseline
                           may be updated to reflect those changes.


                   11.5.3.2 Project documents updates

                     In the Plan Risk Responses process, several project documents are updated as needed. For example, when
                   appropriate risk responses are chosen and agreed upon, they are included in the risk register. The risk register
                   should be written to a level of detail that corresponds with the priority ranking and the planned response. Often, the
                   high and moderate risks are addressed in detail. Risks judged to be of low priority are included in a watch list for
                   periodic monitoring. Updates to the risk register can include, but are not limited to:


















                                                                                       ®
                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   347


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   368   369   370   371   372   373   374   375   376   377   378