11 - PROJECT RISK MANAGEMENT
11.5 Plan risk responses
Plan Risk Responses is the process of developing options and actions to enhance opportunities and to reduce
threats to project objectives. The key benefit of this process is that it addresses the risks by their priority, inserting
resources and activities into the budget, schedule and project management plan as needed. The inputs, tools and
techniques, and outputs of this process are depicted in Figure 11-18. Figure 11-19 depicts the data flow diagram
of the process.
Inputs Tools & Techniques Outputs
.1 Risk management plan .1 Strategies for negative .1 Project management plan
.2 Risk register risks or threats updates
.2 Strategies for positive .2 Project documents
risks or opportunities updates
.3 Contingent response
strategies
.4 Expert judgment
Figure 11-18. Plan risk responses: Inputs, tools & techniques, and outputs
Project Risk Management
11.1 11.2
Plan Risk Identify
Management Risks Project
Documents
• Risk management • Risk register
plan
• Project documents
updates
11.5
Plan Risk 4.2
Responses Develop Project
• Project management Management
plan updates Plan
Figure 11-19. Plan risk responses data Flow diagram
342 ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK Guide) – Fifth Edition
®