Page 366 -
P. 366

11 - PROJECT RISK MANAGEMENT






                           •   Modeling and simulation. A project simulation uses a model that translates the specified detailed
                              uncertainties of the project into their potential impact on project objectives. Simulations are typically
                              performed using the Monte Carlo technique. In a simulation, the project model is computed many times
                              (iterated), with the input values (e.g., cost estimates or activity durations) chosen at random for each
                              iteration from the probability distributions of these variables. A histogram (e.g., total cost or completion
                              date) is calculated from the iterations. For a cost risk analysis, a simulation uses cost estimates. For a
                              schedule risk analysis, the schedule network diagram and duration estimates are used. The output from a
                              cost risk simulation using the three-element model and risk ranges is shown in Figure 11-17. It illustrates
                              the respective probability of achieving specific cost targets. Similar curves can be developed for other
                              project objectives.


                                                              Total Project Cost
                                                               Cumulative Chart
                                        100%
                                                           Mean = $46.67M

                                         75%
                                       Probability  50%




                                         25%
                                           12%
                                          0%
                                                               $41M                 $50M
                                                $30.00M             $38.75M            $47.50M             $56.25M            $65.00M
                                                                    Cost
                                This cumulative distribution, assuming the data ranges in Figure 11-13 and triangular distributions, shows that the
                                project is only 12 percent likely to meet the $41 million most likely cost estimate. If a conservative organization wants
                                a 75% likelihood of success, a budget of $50 million (a contingency of nearly 22 % ($50M - $41M)/$41M)) is required.

                                                   Figure 11-17. cost risk Simulation results


























             340      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   361   362   363   364   365   366   367   368   369   370   371