Page 367 -
P. 367

11 - PROJECT RISK MANAGEMENT






                   11.4.2.3 Expert Judgment

                     Expert judgment (ideally using experts with relevant, recent experience) is required to identify potential cost
                   and schedule impacts, to evaluate probability, and to define inputs such as probability distributions into the tools.

                     Expert judgment also comes into play in the interpretation of the data. Experts should be able to identify the
                   weaknesses of the tools as well as their strengths. Experts may determine when a specific tool may or may not be
                   more appropriate given the organization’s capabilities and culture.



                   11.4.3 Perform Quantitative risk Analysis: outputs


                   11.4.3.1 Project documents updates


                     Project documents are updated with information resulting from quantitative risk analysis. For example, risk
                   register updates could include:

                        •   Probabilistic analysis of the project. Estimates are made of potential project schedule and cost   11
                           outcomes listing the possible completion dates and costs with their associated confidence levels.
                           This output, often expressed as a cumulative frequency distribution, is used with stakeholder risk
                           tolerances to permit quantification of the cost and time contingency reserves. Such contingency
                           reserves are needed to bring the risk of overrunning stated project objectives to a level acceptable to
                           the organization.

                        •   Probability of achieving cost and time objectives. With the risks facing the project, the probability
                           of achieving project objectives under the current plan can be estimated using quantitative risk analysis
                           results. For instance, in Figure 11-17, the likelihood of achieving the cost estimate of US$41 million is
                           about 12%.
                        •   Prioritized list of quantified risks. This list includes those risks that pose the greatest threat or present
                           the greatest opportunity to the project. These include the risks that may have the greatest effect on cost
                           contingency and those that are most likely to influence the critical path. These risks may be evaluated, in
                           some cases, through a tornado diagram generated as a result of the simulation analysis.
                        •   trends in quantitative risk analysis results. As the analysis is repeated, a trend may become apparent
                           that leads to conclusions affecting risk responses. Organizational historical information on project schedule,
                           cost, quality, and performance should reflect new insights gained through the Perform Quantitative Risk
                           Analysis process. Such history may take the form of a quantitative risk analysis report. This report may
                           be separate from, or linked to, the risk register.














                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   341
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   362   363   364   365   366   367   368   369   370   371   372