Page 362 -
P. 362

11 - PROJECT RISK MANAGEMENT






                      11.4.1.6 organizational Process Assets

                         Described in Section 2.1.4. The organizational process assets that can influence the Perform Quantitative Risk
                      Analysis process include information from prior, similar completed projects.



                      11.4.2 Perform Quantitative risk Analysis: tools and techniques



                      11.4.2.1 data Gathering and representation techniques
                           •   Interviewing. Interviewing techniques draw on experience and historical data to quantify the probability
                              and impact of risks on project objectives. The information needed depends upon the type of probability
                              distributions that will be  used. For  instance, information would be  gathered on the  optimistic  (low),
                              pessimistic (high), and most likely scenarios for some commonly used distributions. Examples of three-
                              point estimates for cost are shown in Figure 11-13. Additional information on three-point estimates
                              appears in Estimate Activity Durations (Section 6.5) and Estimate Costs (Section 7.2). Documenting the
                              rationale of the risk ranges and the assumptions behind them are important components of the risk
                              interview because they can provide insight on the reliability and credibility of the analysis.


                                                        Range of Project Cost Estimates

                                                  WBS Element    Low    Most Likely  High

                                                    Design       $4M      $6M       $10M

                                                     Build      $16M      $20M      $35M

                                                     Test       $11M      $15M      $23M

                                                  Total Project  $31M     $41M      $68M

                                       Interviewing relevant stakeholders helps determine the three-point estimates for each WBS
                                       element for triangular, beta or other distributions. In this example, the likelihood of completing
                                       the project at or below the most likely estimate of $41 million is relatively small as shown in
                                       the simulation results in Figure 11-17 (Cost Risk Simulation Results).

                                 Figure 11-13. range of Project cost Estimates collected during the risk Interview


















             336      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   357   358   359   360   361   362   363   364   365   366   367