11 - PROJECT RISK MANAGEMENT








                                        Inputs            Tools & Techniques           Outputs
                                 .1  Risk management plan  .1  Data gathering and    .1  Project documents
                                 .2  Cost management plan   representation        updates
                                 .3  Schedule management      techniques
                                   plan                   .2  Quantitative risk analysis
                                 .4  Risk register          and modeling techniques
                                 .5  Enterprise environmental    .3  Expert judgment
                                   factors
                                 .6  Organizational process
                                   assets

                             Figure 11-11. Perform Quantitative risk Analysis: Inputs, tools & techniques, and outputs






                                                            Project Risk Management
                                       6.1
                                    Plan Schedule         11.1                 11.2
                                     Management         Plan Risk              Identify
                                                       Management              Risks
                                       7.1               • Risk management   • Risk register
                                      Plan Cost            plan
                                     Management
                                                   • Schedule
                                                     management plan
                                                                    11.4
                                                   • Cost management plan  Perform               Project
                                                                  Quantitative                  Documents
                                                                  Risk Analysis  • Project documents
                                                                                updates
                                                   • Organizational
                                                     process assets
                                                   • Enterprise
                                     Enterprise/    environmental
                                     Organization    factors




                                       Figure 11-12. Perform Quantitative risk Analysis data Flow diagram

                         Perform Quantitative Risk Analysis is performed on risks that have been prioritized by the Perform Qualitative
                      Risk Analysis process as potentially and substantially impacting the project’s competing demands. The Perform
                      Quantitative Risk Analysis process analyzes the effect of those risks on project objectives. It is used mostly to
                      evaluate the aggregate effect of all risks affecting the project. When the risks drive the quantitative analysis, the
                      process may be used to assign a numerical priority rating to those risks individually.















             334      ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®