Page 359 -
P. 359

11 - PROJECT RISK MANAGEMENT






                   11.3.2.5 risk urgency Assessment

                     Risks requiring near-term responses may be considered more urgent to address. Indicators of priority may
                   include probability of detecting the risk, time to affect a risk response, symptoms and warning signs, and the
                   risk rating. In some qualitative analyses, the assessment of risk urgency is combined with the risk ranking that is
                   determined from the probability and impact matrix to give a final risk severity rating.


                   11.3.2.6 Expert Judgment

                     Expert judgment is required to assess the probability and impact of each risk to determine its location in
                   the matrix shown in Figure 11-10. Experts generally are those having experience with similar, recent projects.
                   Gathering expert judgment is often accomplished with the use of risk facilitation workshops or interviews. The
                   experts’ bias should be taken into account in this process.



                   11.3.3 Perform Qualitative risk Analysis: outputs
                                                                                                                          11
                   11.3.3.1 Project documents updates


                     Project documents that may be updated include, but are not limited to:
                        •   risk register updates.  As new information becomes available through the qualitative risk
                           assessment, the risk register is updated. Updates to the risk register may include assessments
                           of probability and impacts for each risk, risk ranking or scores, risk urgency information or risk
                           categorization, and a watch list for low probability risks or risks requiring further analysis.
                        •   Assumptions log updates.  As new information becomes available through the qualitative risk
                           assessment, assumptions could change. The assumptions log needs to be revisited to accommodate
                           this new information. Assumptions may be incorporated into the project scope statement or in a
                           separate assumptions log.


                   11.4 Perform Quantitative risk Analysis


                     Perform Quantitative Risk Analysis is the process of numerically analyzing the effect of identified risks on overall
                   project objectives. The key benefit of this process is that it produces quantitative risk information to support decision
                   making in order to reduce project uncertainty. The inputs, tools and techniques, and outputs of this process are
                   depicted in Figure 11-11. Figure 11-12 depicts the data flow diagram of the process.













                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   333
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   354   355   356   357   358   359   360   361   362   363   364