12 - PROJECT PROCUREMENT MANAGEMENT












                                    4.2               Project Procurement Management
                                 Develop Project
                                 Management
                                    Plan        • Project management plan

                                    5.2         • Requirements documentation
                                   Collect
                                 Requirements
                                                                                              Project
                                                                                             Documents
                                    11.2        • Risk register
                                   Identify
                                   Risks        • Activity resource         • Project
                                                   requirements              documents
                                                                 12.1         updates
                                                                 Plan                           4.5
                                    6.4                        Procurement                    Perform
                                Estimate Activity              Management                     Integrated
                                  Resources                                 • Change        Change Control
                                                                              requests
                                    6.6               • Make-or-buy decisions  • Procurement   13.1
                                   Develop            • Procurement      documents            Identify
                                  Schedule              management plan                      Stakeholders
                                                      • Procurement
                                 • Project schedule     statement of work  12.3
                                                      • Source selection      Control
                                                        criteria                               11.2                       12
                                    7.2                                 Procurements
                                  Estimate                                                    Identify
                                                                                               Risks
                                   Costs
                                                       12.2               12.4
                                 • Activity cost estimates  Conduct       Close
                                                     Procurements       Procurements
                                    13.1
                                   Identify
                                 Stakeholders
                                                  • Organizational
                                 • Stakeholder register    process assets
                                                  • Enterprise
                                                   environmental
                                  Enterprise/       factors
                                  Organization
                                      Figure 12-3. Plan Procurement Management data Flow diagram

                     Plan Procurement Management identifies those project needs that can best be met or should be met by
                   acquiring products, services, or results outside of the project organization, versus those project needs which can
                   be accomplished by the project team. When the project obtains products, services, and results required for project
                   performance from outside of the performing organization, the processes from Plan Procurement Management
                   through Close Procurements are performed for each item to be acquired.















                                                                                       ®
                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   359


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   380   381   382   383   384   385   386   387   388   389   390