2 - ORGANIZATIONAL INFLUENCES AND PROJECT LIFE CYCLE






                      2.2 Project Stakeholders and Governance

                         A stakeholder is an individual, group, or organization who may affect, be affected by, or perceive itself to be
                      affected by a decision, activity, or outcome of a project. Stakeholders may be actively involved in the project or have
                      interests that may be positively or negatively affected by the performance or completion of the project. Different
                      stakeholders may have competing expectations that might create conflicts within the project. Stakeholders may
                      also exert influence over the project, its deliverables, and the project team in order to achieve a set of outcomes
                      that satisfy strategic business objectives or other needs. Project governance—the alignment of the project with
                      stakeholders’ needs or objectives—is critical to the successful management of stakeholder engagement and
                      the achievement of organizational objectives. Project governance enables organizations to consistently manage
                      projects and maximize the value of project outcomes and align the projects with business strategy. It provides a
                      framework in which the project manager and sponsors can make decisions that satisfy both stakeholder needs
                      and expectations and organizational strategic objectives or address circumstances where these may not be in
                      alignment.



                      2.2.1 Project Stakeholders

                         Stakeholders include all members of the project team as well as all interested entities that are internal or
                      external to the organization. The project team identifies internal and external, positive and negative, and performing
                      and advising stakeholders in order to determine the project requirements and the expectations of all parties
                      involved. The project manager should manage the influences of these various stakeholders in relation to the project
                      requirements to ensure a successful outcome. Figure 2-7 illustrates the relationship between the project, the
                      project team, and various stakeholders.




































             30       ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®