2 - ORGANIZATIONAL INFLUENCES AND PROJECT LIFE CYCLE








                                                   Project Life Cycle and Organization

                                                          Project Stakeholders                                            2


                                                Other                            Operations
                                     Portfolio  Stakeholders     Sponsor        Management  Functional
                                     Manager                                               Managers
                                                              Project Team
                                                        Project            Other
                                                        Manage-            Project          Sellers/
                                      Program                     Project  Team            Business
                                     Manager             ment    Manager  Members
                                                         Team                               Partners
                                              Project
                                             Manage-                              Customers/
                                               ment                                 Users
                                              Office


                                                              The Project




                                     Figure 2-7. the relationship Between Stakeholders and the Project

                      Stakeholders have varying levels of responsibility and authority when participating on a project. This level can
                   change over the course of the project’s life cycle. Their involvement may range from occasional contributions in
                   surveys and focus groups to full project sponsorship which includes providing financial, political, or other support.
                   Some stakeholders may also detract from the success of the project, either passively or actively. These stakeholders
                   require the project manager’s attention throughout the project’s life cycle, as well as planning to address any issues
                   they may raise.

                      Stakeholder identification is a continuous process throughout the entire project life cycle. Identifying stakeholders,
                   understanding their relative degree of influence on a project, and balancing their demands, needs, and expectations
                   are critical to the success of the project. Failure to do so can lead to delays, cost increases, unexpected issues,
                   and other negative consequences including project cancellation. An example is late recognition that the legal
                   department is a significant stakeholder, which results in delays and increased expenses due to legal requirements
                   that are required to be met before the project can be completed or the product scope is delivered.





















                   ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition   31
                                                                                       ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   52   53   54   55   56   57   58   59   60   61   62