Page 78 -
P. 78

3 - PROJECT MANAGEMENT PROCESSES






                      3.2 Project Management Process Groups

                         The following sections identify and describe the five Project Management Process Groups required for any
                      project. These five Process Groups have clear dependencies and are typically performed in each project and
                      highly interact with one another. These five Process Groups are independent of application areas or industry focus.
                      Individual Process Groups and individual processes are often iterated prior to completing the project and can have
                      interactions within a Process Group and among Process Groups. The nature of these interactions varies from project
                      to project and may or may not be performed in a particular order.

                         The process flow diagram, Figure 3-3, provides an overall summary of the basic flow and interactions
                      among  Process  Groups  and  specific  stakeholders. The  project  management  processes  are  linked  by  specific
                      inputs and outputs where the result or outcome of one process becomes the input to another process but not
                      necessarily in the same Process Group. the Process Groups are not project life cycle phases. In fact, it is
                      possible that all Process Groups could be conducted within a phase. As projects are separated into distinct phases
                      or subcomponents, such as concept development feasibility study, design, prototype, build, or test, etc., all of the
                      Process Groups would normally be repeated for each phase or subcomponent along the lines explained previously
                      and illustrated in Figure 3-2.

                         The project management processes are shown in the Process Group in which most of the related activities takes
                      place. For example, a process that normally takes place in the planning phase is put into the Planning Process
                      Group. When this process is updated by an Executing Process Group process or activity, it is not considered a new
                      process within the Executing Process Group but is still a Planning Process Group process or activity. The iterative
                      nature of project management means that processes from any group may be reused throughout the project life
                      cycle. For example, in response to a risk event, executing a risk response may trigger further analysis, which leads
                      to another iteration of the Identify Risks process and the associated Perform Quantitative Risk Analysis and Perform
                      Quantitative Risk Analysis processes to evaluate the impact.

































             52       ©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK  Guide) – Fifth Edition
                                                                                          ®


                                           Licensed To: Jorge Diego Fuentes Sanchez PMI MemberID: 2399412
                                       This copy is a PMI Member benefit, not for distribution, sale, or reproduction.
   73   74   75   76   77   78   79   80   81   82   83